Thursday, December 23, 2010

June 2010

 

Weekly meeting.

 

Harris 107, above.

The schedule . . . before the strike.

Superintendent Ron McAllister.

Selecting marble flooring for the lower level.

Dan Weese and I test the seating mock-up in Harris 108.

Elevator rails await installation.

The new elevator shaft.

Assembling the elevator cab.

Assembling the elevator

Unloading a window delivery.

Faculty Lounge in construction.

Beginning to install forms for the new stairs serving the lower level.

 

A few spools of the many miles of wiring in Harris Hall.

Painstaking work . . . stripping years of paint away in Harris 107.

Forming stairs continues.

Freshly poured concrete stairs.

Troweling fresh concrete.

Installing windows.

Installing drywall at the 3rd floor.

Wood trim at offices.

0 comments:

Post a Comment